Development agreement Schaumburg, IL Met Oct 19 Found Oct 19
$100M minimum additional capital improvements to the Facility
Mar 31 LPC must commence construction… 8 itemssince Oct 19
developer LPC Acquisition Company
Development agreement Schaumburg, IL Met Oct 19 Found Oct 19
$100M minimum capital improvements to the Facility by December 31, 2030
Dec 31 deadline to hire a minimum of… 8 itemssince Oct 19
applicant LPC Acquisition Company
Subdivision Aubrey, TX Met Oct 22 Found Oct 16
$63M design, acquisition and construction of the Authorized Improvements plus bond issuance, legal, financial, credit enhancement, and district establishment/administration costs
735 lots Nov 19 Decides 34 days after we found it owner Aubrey 166 Land Investors
Development agreement Sheboygan, WI Met Nov 3 Found 12d ago
$29M minimum incremental real estate assessed value triggering incentive payments and tax increment deficiency obligations
240 units 3 itemssince Oct 26 developer Oscar Apartments
Development agreement Sheboygan, WI Met Oct 26 Found Oct 23
$29M minimum incremental real estate assessed value triggering incentive payments and tax increment deficiency obligations
240 units 3 itemssince Oct 26 developer Oscar Apartments
Development agreement Dundas, MN Met Oct 26 Found Oct 23
$17M estimated after-completion market value provided by the County Assessor
Jun 30 deadline for Developer to…
developer Cannon River Lofts Development
Rezoning Palo Alto, CA Met Nov 9 Found 11d ago
$12M estimated development impact fees, plus the Public Art fee
6,695 units Oct 30 Decided 1 day after we found it applicant High Street Residential / TC NO. CAL. DEVELOPMENT
Development agreement Carefree, AZ Met Oct 22 Found Oct 16
$12M not-to-exceed total of Construction Sales Tax Reimbursement, Fee Waiver, and Sales Tax Rebates equal to eligible Public Improvement Costs
Jan 1 Deemed Initiation Date if…
developer SimonCRE Maroon IV
Rezoning Danville, VA Met Nov 5 Found 11d ago
$11M maximum aggregate principal amount of general obligation bonds
Nov 5 Decided 7 days after we found it
applicant BIRD
Development agreement La Crosse, WI Meets Nov 12 Found 4h ago
$8.5M minimum assessed value of the Project guaranteed beginning tax year 2030 for 20 years or life of TID #18
60 units Dec 31 Architectural design approvals… 2 itemssince Nov 5 developer RyKey Properties
Development agreement La Crosse, WI Met Nov 5 Found Oct 16
$8.5M minimum assessed value of the Project guaranteed beginning tax year 2030 for 20 years or life of TID #18
60 units Dec 31 Architectural design approvals… 2 itemssince Nov 5 developer RyKey Properties
Development agreement Bondurant, IA Met Oct 26 Found Oct 23
$6.1M TIF reimbursement for eligible public infrastructure costs
Nov 16 Decides 24 days after we found it
developer Opus Development Company, L.L.C.
Rezoning Maricopa County, AZ Met Oct 21 Found Oct 16
$500M Toyota's physical improvements at the Testing Facility
owner Toyota Motor Engineering & Manufacturing North America
Development agreement Fresno, CA Met Oct 22 Found Oct 16
$4.3M conditional City funds contribution for eligible construction expenses (grant and/or loan)
100 units Sep 30 Resolution, funds contribution… 3 itemssince Sep 3 developer Samuelian Group
EntitlementStudy Oxnard, CA Meets Nov 17 Found 3d ago
$40M existing maximum bonded indebtedness (2025 Modifications)
Dec 15 Decides 39 days after we found it
owner MRP HTMBowner Northshore Environmental Conservancy +2 more
Budget actionAdoption Sacramento, CA Met Oct 27 Found Oct 22
$38M maximum tax-exempt mortgage revenue bond issuance
198 units Oct 27 Decided 5 days after we found it developer Community HousingWorks
Rezoning Aliso Viejo, CA Met Oct 21 Found Oct 22
$3.7M public benefit contribution to the City under the Development Agreement
Nov 18 Decides 27 days after we found it On agendas since Oct 22 7 itemssince Aug 19
applicant Shea Homesarchitect Woodley Architectural Group
Rezoning Aliso Viejo, CA Met Oct 21 Found Oct 16
$3.7M public benefit contribution to the City under the Development Agreement
Nov 18 City held a duly noticed public… Oct 21 Decided 5 days after we found it On agendas since Oct 22 7 itemssince Aug 19
applicant Shea Homesarchitect Woodley Architectural Group
EntitlementSolicitation Miami Beach, FL Meets Dec 8 Found Oct 15
$36M current approximate project cost estimate
Dec 8 Decides 54 days after we found it
applicant Media Holdings 930 LLC & Media Holdingsarchitect Arquitectonica +1 more
EntitlementAdoption Brownsville, TX Met Nov 4 Found 12d ago
$2.5B estimated captured appraised value by Tax Year 30 of the Zone
developer ML Rhodesowner Forshage Land Investments +1 more
EntitlementAdoption New York, NY Met Oct 22 Found Oct 22
$23M cumulative cost to the City of the prospective 40-year exemption
77 units Dec 31 project must incur at least 10%… owner Albans Housing Development Fundowner WFHA St. Albans
EntitlementStudy Concord, NH Met Oct 21 Found Oct 16
$23M FY2025 appropriation for CIP #91 sewer mains and #275 sewer pump stations, combined
Nov 18 recommended continuation date… Oct 21 Decided 5 days after we found it 4 itemssince Oct 21
owner Onyx Steeplegate Concordowner Onyx Regal Concord +2 more
EntitlementStudy Concord, NH Met Oct 21 Found Oct 16
$23M sewer main and pump station replacement (CIP #91 and #275 combined)
29,250 gal_PER_DAY Nov 18 Date certain proposed for… Oct 21 Decided 5 days after we found it 4 itemssince Oct 21 applicant Onyx Steeplegate Concordapplicant Gallagher Callahan & Gartrell PC +2 more
Rezoning Miami Beach, FL Meets Dec 8 Found Oct 26
$2.1M 2025 market/assessed/taxable value of the property
Nov 3 Decided 8 days after we found it 4 itemssince Nov 3
applicant La Gorce Country Clubapplicant Bercow Radell Fernandez Larkin & Tapanes
Rezoning Glendale, AZ Met Oct 27 Found Oct 16
$169M estimated total construction cost for the 1,023,900-square-foot building
applicant Formation Interestsapplicant Tiffany & Bosco, P.A. +2 more