Contract awardedAward Orange County Transportation Authority, CA Met Oct 29 Found Oct 22
$790M overall SR-91 improvement project costs, approximately
contractorMyers & Sons Construction
Change order Pharr, TX Met Nov 2 Found 13d ago
$45M revised contract total after Change Order #4
2 itemssince Nov 2
contractorD. Wilson Construction
Change order Torrance, CA Met Nov 3 Found 12d ago
$36M revised total contract amount including base contract and contingency
Jan20 start of construction milestone 2 itemssince Jul 21
developerMcCarthy Building Companies
Change order Atlanta, GA Met Oct 27 Found Oct 23
$20M combined additional funding for both agreements
May1 Start of the second renewal term…
contractorSoutheastern Site Development, Inc. & Precision 2000, Inc., Joint VenturecontractorIntegral Municipal Services Corporation/Rockdale Pipeline Inc. JV
Change order Huntsville, AL Met Oct 22 Found Oct 20
$15M cumulative not-to-exceed amount funded for the contract after the extension
Oct23 new contract expiration date…
contractorMark Johnson Construction, L.L.C.
Change order Ventura, CA Met Oct 26 Found Oct 23
$15M total not-to-exceed contract amount during the total duration of the contract
Jul31 contract completion date for the…
contractorMWH Constructors
Change order Kansas City, MO Met Oct 22 Found Oct 21
$13M Total revised contract amount after Amendment No. 2
Aug30 Estimated completion of Phase…
developerBurns & McDonnell Engineering CompanybidderGoodwin Brothers Construction Company/CMT +2 more
Change order Oklahoma City, OK Met Oct 27 Found Oct 23
$11M revised contract amount after all amendments and change orders
Feb17 contract completion date…
contractorSchwarz Paving Company
Change order Oklahoma City, OK Met Oct 27 Found Oct 22
$11M revised contract amount after all amendments and change orders
Feb17 contract completion date…
contractorSchwarz Paving CompanycontractorINSURICA
Contract awardedAmendment Orange County Sanitation District, CA Met Nov 4 Found 12d ago
$97M construction contract with Walsh Construction Company II, LLC
contractorWalsh Construction Company II
Change order Fresno, CA Met Oct 22 Found Oct 16
$6.4M revised contract price after CCO No. 2
Dec3 Extended date for completion… 3 itemssince Oct 22
contractorAvison Construction
GMP / CMAR League City, TX Met Oct 27 Found Oct 21
$5.8M Freese and Nichols construction management, inspection, start-up, and post-construction services not to exceed
contractorCSA Construction
Contract awardedSolicitation DeKalb County, GA Met Oct 20 Found Oct 16
$52M Hawk Construction Company BAFO
Nov30 Solicitation prices expire 4 itemssince Oct 20
subcontractorVLW GroupsubcontractorQ Solutions +2 more
Contract awardedAward Palm Springs, CA Met Oct 28 Found Oct 22
$47M Ortiz construction contract including additive Bid Schedule B
Oct28 Decided 6 days after we found it
subcontractorAll American Asphaltlow bidderAmes Construction +2 more
Change order Brighton Urban Renewal Authority, CO Met Oct 21 Found Oct 15
$4.1M new not-to-exceed total of the contract
Jun9 contract completion date… 2 itemssince Oct 21
contractorROCK &
Change order Brownsville, TX Met Nov 3 Found 12d ago
$3.4M Dennet Road line item 812-8200-9994-63 after Change Order No. 1
Apr18 Original contract completion date
contractor2GS LLC dba Earthworks EnterprisebidderClore Equipment +2 more
Change order Burleson, TX Met Nov 9 Found 11d ago
$3.2M total contract amount including all change orders
2 itemssince Nov 9
contractor2L Construction
Contract awardedAward Bend, OR Met Oct 21 Found Oct 21
$25M full faith & credit obligations for eligible projects including acquisition, improvement and furnishing of real property for city administrative functions and paying costs of issuance
Jan31 contractor must complete all… On agendas since Oct 22 2 itemssince Oct 21
low bidderJaron McKernan Enterprises
Change order Oklahoma City, OK Met Oct 27 Found Oct 22
$2.5M revised total contract amount after Change Orders 1-2
Feb6 revised contract completion date
contractorUrban Contractors
Change order Temple Terrace, FL Met Nov 2 Found 12d ago
$2.0M PaymentWorks indemnification of vendor payments per transaction
Nov17 Council meeting at which the…
contractorAtlantic Pipe Services
Change order Laguna Hills, CA Met Oct 27 Found Oct 23
$1.9M warrant register payments September 14, 2026 to October 4, 2026
contractorTranstech Engineers
Contract awardedAward Santa Margarita Water District, CA Met Nov 4 Found 11d ago
$15M total contract capacity over five years
contractorJacobs Project Management
Change order Monterey County, CA Met Oct 27 Found Oct 22
$1.4M potential overall aggregate not-to-exceed amount after amendments
Jan31 State grant Work Completion Date
subcontractorLuhdorff & Scalmanini Consulting Engineers, Inc. (LSCE)subcontractorPacific Engineering & Consulting, Inc. (Pacific) +2 more
Change order Coachella Valley Water District, CA Met Oct 27 Found Oct 20
$1.4M one-time additional expenditures for project management, engineering, CVWD forces, environmental surveys, task orders, inspection, tribal monitoring, and contingency
Dec1 tribal monitoring project start…
low bidderBorden ExcavatingsubcontractorMatich
Contract awardedAmendment Kansas City, MO Met Oct 27 Found Oct 21
$13M total contract amount after Amendment No. 2
Aug31 estimated completion of… On agendas since Oct 21 2 itemssince Oct 27
developerBurns & McDonnell Engineering CompanybidderGoodwin Brothers Construction Company/CMT +1 more