December 2025 BPW Change Order Report.
Topics
Summary
Summary
This report details non-Board of Public Works (BPW) change orders for December 2025. Two change orders are listed:
Project 9626 (Mid Town Hydraulic Improvements): Change Order (CO)-001 for clearing, grubbing, and rock excavation. This was due to a missing or additional bid item needed and a field decision expanding the scope. The cost of this change order is $10,150.00, representing 2.35% of the original contract amount of $431,999.99. It was sent on December 12, 2025, and is related to Water infrastructure.
Project 9657 (Stricker Pond Forebay Dredging): Change Order (CO)-001 for a bid item account transfer. This change order has a cost of $0.00, representing 0.0% of the original contract amount of $437,886.00. It was sent on December 17, 2025, and is related to Street infrastructure.
Citizen Impact
These are administrative adjustments to existing contracts. The Mid Town Hydraulic Improvements project has a minor cost increase of $10,150, while the Stricker Pond Forebay Dredging project has no cost change. Residents may experience temporary disruptions related to these infrastructure projects.
Confidence
high