Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for CIPP UV Lining Rehabilitation of Sewers Phase 1 - 2026. (District 3, District 5, District 11, District 15, District 19)
Sponsors
Topics
Summary
Summary
This item approves the plans, specifications, and authorizes the Board of Public Works to advertise and receive bids for the CIPP UV Lining Rehabilitation of Sewers Phase 1 - 2026. This project involves trenchless rehabilitation of existing sanitary sewers using UV cure lining technology. The scope includes approximately 11,865 linear feet (LF) of pipe rehabilitation across various diameters (8" and 10"), as well as 197 laterals and 6 outside drops. The estimated cost for this phase is $1,249,095.00, broken down as follows:
- 8" pipes: 8,145 LF, $570,150.00
- 10" pipes: 3,720 LF, $312,480.00
- Laterals: 197, $65,010.00
- Outside Drops: 6, $1,980.00
- Miscellaneous: $299,475.00
The project will primarily affect Districts 3, 5, 11, 15, and 19. This is the first phase of a multi-year rehabilitation effort.
Citizen Impact
This project will improve the structural integrity of sewer lines, reducing the risk of future breaks and service disruptions in Districts 3, 5, 11, 15, and 19. Residents may experience temporary traffic delays in affected areas during construction, but the trenchless method aims to minimize surface disruption.
Confidence
high
Committee Timeline
Want to know when this matter moves?