Miscellaneous 91442 1 appearance active

Change Order No. 1 to Contract 9591, Capital City Trail Box Culvert Replacement, to Speedway Sand & Gravel., for $211,687.42 and a time extension of 12 days. (District 6).

Madison, WI January 14, 2026 - January 14, 2026

Summary

This is a change order (No. 1) to Contract 9591 for the Capital City Trail Box Culvert Replacement project. The change order is with Speedway Sand & Gravel and adds $211,687.42 to the contract, increasing the total contract sum to $1,633,169.32. This represents a 14.89% increase over the original contract amount. Additionally, the project timeline is extended by 12 calendar days, bringing the new completion date to 87 days from the original contract time. The change order is attributed to factors such as differing site conditions, missing bid items, and design not adequately anticipating field conditions. The project is located in Aldermanic District 6.

Citizen Impact

Residents may experience continued construction disruptions for an additional 12 days due to this change order. The project's increased cost of over $211,000 means the remaining project contingency is now negative, potentially impacting future budget allocations for other projects.

Confidence

high

BOARD OF PUBLIC WORKS
January 14, 2026