Resolution No. 4700-26, West Mitchell Hammock Water Treatment Facility 2.5 Million Gallon Ground Storage Tank
Topics
Summary
Summary
This resolution approves Change Order No. 2 for the West Mitchell Hammock Water Treatment Facility (WMHWTF) 2.5 Million Gallon Ground Storage Tank project. The change order totals $119,898 and addresses several necessary modifications identified during construction.
Key changes include:
- $166,902 for replacing leaking 36-inch and 24-inch existing butterfly valves with new line stops, tapping saddles, and valves.
- $22,212 for electrical modifications, replacing fiber equipment with hardwire IO signals.
- $2,784 for the removal and reinstallation of an existing light pole within the work zone.
- A deductive change of $72,000 for revising the interior tank painting scope to only coat the dome and the upper five feet of the tank, based on subcontractor recommendation.
Additionally, a $50,000 contingency is being added to the project. A budget amendment of $169,898 is required, transferring funds from the Water/Wastewater Operating Fund balance to the construction account. The original contract with L7 Construction, Inc. was for $4,608,700.
Citizen Impact
This change order ensures the continued reliable operation of the West Mitchell Hammock Water Treatment Facility by addressing necessary repairs and modifications to a new storage tank. Residents will benefit from improved water infrastructure integrity, with no direct increase in costs as the funding comes from existing balances and project contingency.
Confidence
high
Committee Timeline
No timeline data available.
Want to know when this matter moves?
Set Up Alerts