General Item 2026-002 1 appearance active

Update on Highway 140 Projects - City Engineer Bethany Watson

Canton, GA February 5, 2026 - February 5, 2026

Summary

This agenda item provides an update on ongoing projects related to Highway 140, specifically focusing on improvements for SR 5 CONN and SR 5 BU. For SR 5 CONN, the project is programmed for a total of $4,777,589, with staff seeking additional funds to increase the total project cost to $8,167,642.33. This represents an increase of $3,390,053.33, primarily for construction (CST). For SR 5 BU, the project is programmed for a total of $11,874,751.

Citizen Impact

These updates indicate potential increases in funding requests for Highway 140 projects, which could impact future budgets or project timelines. Residents can expect continued work and potential disruptions related to these transportation infrastructure improvements.

Confidence

high

City Council
February 5, 2026